3. (50 points) Correctly fill in the materials plans for all the items. All lot sizing is lot-for-lot.
Item Lead time Inventory on hand X Y
X 1 45 A B C
Y 1 35 (1) (2) (2)
A
2 45
B 2 410 B
C 3 220 (3)
Master Schedule
Period 1 2 3 4 5 6 7 8 9 10 11 12
X 10 10 20 10 35 20 10 30 5 15
Y 15 25 20 20 40 20 10 45 15 15
MRP Worksheets
Item: X Lead time= Lot Sizing rule =
Gross Requirements
Scheduled Receipts
Projected on Hand
Net Requirements
Planned Order Receipts
Planned Order Releases
Item: Y Lead time= Lot sizing rule =
Gross Requirements
Scheduled Receipts 20
Projected on Hand
Net Requirements
Planned Order Receipts
Planned Order Releases
Item: A Lead time= Lot sizing rule =
Gross Requirements
Scheduled Receipts
Projected on Hand
Net Requirements
Planned Order Receipts
Planned Order Releases
Item: B Lead time= Lot Sizing rule =
Gross Requirements
Scheduled Receipts
Projected on Hand
Net Requirements
Planned Order Receipts
Planned Order Releases
Period 1 2 3 4 5 6 7 8 9 10 11 12
Item: C Lead time= Lot Sizing rule =
Gross Requirements
Scheduled Receipts
Projected on Hand
Net Requirements
Planned Order Receipts
Planned Order Releases
3. (50 points) Correctly fill in the materials plans for all the items. All lot sizing is lot-for-lot.
Item Lead time Inventory on hand X Y
X 1 45 A B C
Y 1 35 (1) (2) (2)
A
2 45
B 2 410 B
C 3 220 (3)
Master Schedule
Period 1 2 3 4 5 6 7 8 9 10 11 12
X 10 10 20 10 35 20 10 30 5 15
Y 15 25 20 20 40 20 10 45 15 15
MRP Worksheets
Item: X Lead time= Lot Sizing rule =
Gross Requirements
Scheduled Receipts
Projected on Hand
Net Requirements
Planned Order Receipts
Planned Order Releases
Item: Y Lead time= Lot sizing rule =
Gross Requirements
Scheduled Receipts 20
Projected on Hand
Net Requirements
Planned Order Receipts
Planned Order Releases
Item: A Lead time= Lot sizing rule =
Gross Requirements
Scheduled Receipts
Projected on Hand
Net Requirements
Planned Order Receipts
Planned Order Releases
Item: B Lead time= Lot Sizing rule =
Gross Requirements
Scheduled Receipts
Projected on Hand
Net Requirements
Planned Order Receipts
Planned Order Releases
Period 1 2 3 4 5 6 7 8 9 10 11 12
Item: C Lead time= Lot Sizing rule =
Gross Requirements
Scheduled Receipts
Projected on Hand
Net Requirements
Planned Order Receipts
Planned Order Releases